Langdale Berth 1 life extension project | Construction has begun

Construction has started at Langdale Berth 1 as part of the Life Extension Project. Construction will be completed between sailings and at night; however, Berth 1 will be closed for three weeks between February 3 - 23, 2027.

There are no anticipated impacts to sailings.

Construction dates:

  • October 14, 2026, to March 31, 2027
  • No work will occur during the holiday period: December 18, 2026, and January 5, 2027.

Construction hours:

  • General construction hours
    • 7:00 a.m. and 7:00 p.m.
    • Night work, where required, may occur between 11:30 p.m. and 6:00 a.m.
  • Berth closure construction hours
    • 24 hours a day
    • High noise generating work during the berth closure will be limited to 7:00 a.m. to 7:00 p.m.

Construction workdays:

  • Work will occur five days per week, with occasional weekend work.
  • No work will take place on Sundays.
  • During the Berth 1 closure, work will occur seven days per week.

Find out more about the work here.

Share Langdale Berth 1 life extension project | Construction has begun on Facebook Share Langdale Berth 1 life extension project | Construction has begun on X (formerly Twitter) Share Langdale Berth 1 life extension project | Construction has begun on Linkedin Email Langdale Berth 1 life extension project | Construction has begun link