Heriot Bay - Whaletown Terminal Projects
The Heriot Bay and Whaletown terminals play a critical role in connecting the Quadra Island and Cortes Island communities. The marine infrastructures at both terminals are nearing the end of their service life. As populations on both islands grow, we want to ensure the terminals remain safe and easy to access for all members of the public.
Upcoming terminal upgrades are focused on replacing marine terminal infrastructure to accommodate new, higher capacity Island Class vessels, expected to help reduce roadway congestion to create safer, easier access to the terminals for vehicles and walk-on passengers.
The Heriot Bay and Whaletown terminals play a critical role in connecting the Quadra Island and Cortes Island communities. The marine infrastructures at both terminals are nearing the end of their service life. As populations on both islands grow, we want to ensure the terminals remain safe and easy to access for all members of the public.
Upcoming terminal upgrades are focused on replacing marine terminal infrastructure to accommodate new, higher capacity Island Class vessels, expected to help reduce roadway congestion to create safer, easier access to the terminals for vehicles and walk-on passengers.
-
September Project Update: Next steps
Share September Project Update: Next steps on Facebook Share September Project Update: Next steps on Twitter Share September Project Update: Next steps on Linkedin Email September Project Update: Next steps linkOver the past month, the project team has been focused on refining the project and alternate service plans, and incorporating key feedback gathered from the community. This feedback has helped shape important adjustments aimed at addressing the community's priorities and concerns. As we move forward, we are committed to ensuring that the revised plans better serve the needs of our customers.
What we heard, and how we are responding:
Shift in Closure Period: We heard from the community the concern over the proposed timing of the closure, including the unreliable weather and increased possibilities for water taxi cancellations. In response to the feedback received, we have adjusted the closure period from originally starting in January to now beginning in February. Based on historical patterns, it is expected that the weather will be better in the later winter months, resulting in fewer expected sailing cancellations and improved service reliability. In addition, during this planned time period, passenger volumes continue to be lower.
Previous planned closure: January – March
Adjusted planned closure: February - April
Improved Access to Medical Services: During the engagement customers shared their feedback about access to required medical services. To ensure this concern is addressed we are taking the following actions:
- Connecting with Island Health to ensure they have what they need to plan for service.
- Developing a procedure to address customer needs to move their car for unexpected essential needs.
- Develop contingencies for those not able to travel by water taxi for essential purposes
Connections for Essential Services: This has been a key concern, and we’ve prioritized logistics to reduce potential disruptions including working with commercial customers on schedules and timing to ensure food deliveries and other essential goods continue to be available to those on Cortes Island.
Improved Travel Supports: Recognizing the need for better transportation options to and from Mansons Landing, as well as once arriving in Campbell River, we’ve expanded the plan to provide more travel options. This adjustment will help facilitate the movement of people and goods between these locations more efficiently.
Part of this plan includes collaborating with local partners who know and understand the needs of their community and providing funding opportunities to local groups or businesses that can provide on island transportation or in Campbell River throughout the project.
For the second phase of the project, which is expected to take place between March – April, we will re-open the berth at Whaletown, and offer direct service between Cortes Island and Campbell River. We heard clearly from the community this was the preferred option.
Next Steps and timeline for decisions
September – November:
As part of the next steps in this process, we have submitted a report to the BC Ferry Commissioner who will review the plans and provide a decision authorizing the project to move forward with the alternate service plan.
During this time, we will be continuing our conversations with the community, including conversations with the neighbours at Heriot Bay Terminal, health services, and commercial users.
November - December:
Later this fall we will provide an update on the project and the alternate service plans.
We are grateful for the input provided and as we progress we will be providing project updates on this page. You can subscribe to receive these updates via email by clicking 'Subscribe'.
-
'What we heard' report now available
Share 'What we heard' report now available on Facebook Share 'What we heard' report now available on Twitter Share 'What we heard' report now available on Linkedin Email 'What we heard' report now available linkWe are excited to be moving closer to welcoming an Island Class Vessel in 2027 and providing increased capacity for Cortes Islanders and those travelling the route.
In preparation for introducing the larger vessel to the route and to replace aging infrastructure, berth replacements are required for Whaletown and Heriot Bay. This will mean full berth closures and alternate service for the route from January to mid-March, 2026. With work planned to begin in the fall of 2025, engagements with the community have begun early to help shape plans for the alternate service that will be required during the berth closure.
An in-person Open House was held on Cortes Island on April 27, 2024, alongside a three-week online engagement opportunity. Members of the public were invited to attend and provide their input on alternate service plans and ideas to help mitigate impacts on ferry users. The 'what we heard' report from this early engagement period is now available. Click here to read the report.
-
Help us shape alternate service plans for 2026
Share Help us shape alternate service plans for 2026 on Facebook Share Help us shape alternate service plans for 2026 on Twitter Share Help us shape alternate service plans for 2026 on Linkedin Email Help us shape alternate service plans for 2026 linkThe berths at Whaletown and Heriot Bay are being replaced. Help us shape alternative service plans by attending in-person, or taking part online.
Join us in-person on Saturday, April 27 on Cortes Island for an opportunity to learn more about our initial plans for alternate service. You will be able to walk around the room to learn about each leg of your journey, and speak with our teams who will be on hand to listen to your feedback and answer questions.
Participate online Visit our discussion forums between April 19 – May 6.
What's Happening at Whaletown and Heriot Bay?
We are excited to be moving closer to welcoming an Island Class Vessel in 2027 and providing increased capacity for Cortes Islanders and those travelling the route.
In preparation for introducing the larger vessel to the route and to replace aging infrastructure, berth replacements are required for Whaletown and Heriot Bay. Work is planned to begin the fall of 2025 and is expected to be completed spring 2026, with full berth closures and alternate service for the route planned from January to mid-March, 2026.
At Heriot Bay, the work is expected to include:
- New two-lane trestle and ramp with customer waiting shelter and separated foot passenger walkway
- New marine structures for vessel berthing and mooring
At Whaletown, the work is expected to include:
- New two-lane ramp with separated foot passenger walkway
- New marine structures for vessel berthing and mooring
We are in the early stages of planning for alternate service and want to hear from the community to help us shape our plans.
We understand the vital role we play in providing an essential service to those that live and travel to Cortes Island, and are committed to keeping the community informed. As we progress we will be providing project updates on this page.
To stay up to date, you can subscribe to receive proactive updates via email by clicking 'Subscribe' on the right hand side of this page.
We look forward to hearing from you, and working together as we look ahead at exciting improvements coming for the community.
Follow Project
Project Timeline
-
Introduction and Planning begin
Heriot Bay - Whaletown Terminal Projects has finished this stage2023 - March 2024
-
Community Engagement and Feedback
Heriot Bay - Whaletown Terminal Projects has finished this stageCommunity engagement through in person open house, workshops, and online engagement
April 2024
-
Review and Analysis
Heriot Bay - Whaletown Terminal Projects has finished this stageReview feedback on draft plan and report back on what we have heard
August 2024
-
Request for Proposal Process Begins
Heriot Bay - Whaletown Terminal Projects has finished this stageRequest for proposals posted for project related work
September - December 2024
-
Community Update
Heriot Bay - Whaletown Terminal Projects has finished this stageEarly 2025 update on project plans and in-community information session
January 2025 - April 2025
-
In Person Community Information Sessions
Heriot Bay - Whaletown Terminal Projects has finished this stageInformation sessions on Quadra and Cortes Island to provide an update on project plans and what to expect during February berth closure
May 2025
-
Constructions Begins
Heriot Bay - Whaletown Terminal Projects is currently at this stageWork expected to begin at terminals. No impact to service
Late May 2025 - February 2026
-
Berth Closure Begins
this is an upcoming stage for Heriot Bay - Whaletown Terminal ProjectsFebruary 2026
-
Berth Reopens
this is an upcoming stage for Heriot Bay - Whaletown Terminal ProjectsEarly March 2026
-
Project Complete and Island Class arrives
this is an upcoming stage for Heriot Bay - Whaletown Terminal ProjectsSummer 2026
Photos
Documents
-
Engagement
-
2024 BC Ferries Public Event Code of Conduct (514 KB) (pdf)
-
Heriot Bay_WhaletownTerminalProjects_What we heard_FINAL.pdf (2.1 MB) (pdf)
-
Engagement Boards: Heriot Bay - Whaleton Alternate Service Planning 2024 (5.56 MB) (pdf)
-
Engagement Poster: Heriot - Bay Whaletown Alternate Service Planning 2024 (706 KB) (pdf)
-
Engagement Boards Heriot Bay-Whaletown Information Sessions May 2025 (2.63 MB) (pdf)
-
May 2025 - What We Heard Report (641 KB) (pdf)
-
Alternate Service Barge Update - Heriot Bay and Whaletown.pdf (3.38 MB) (pdf)
-
Heriot Bay Whaletown_Engagement Boards_October2025.pdf (1.4 MB) (pdf)
-
-
Project Updates
-
November 7, 2023 - Project Introduction for Heriot Bay and Whaletown Terminals.pdf (76.4 KB) (pdf)
-
November 7, 2023 - Marine Geotechnical Investigations at Heriot Bay & Whaletown Terminals.pdf (91 KB) (pdf)
-
April 19, 2024 - Help us shape alternate service plans for 2026.pdf (93.9 KB) (pdf)
-
June 19 2025 - Project Update (2.11 MB) (png)
-
July 2025 - Project Update (2.18 MB) (png)
-
August 2025 - Project Update (112 KB) (jpeg)
-