Fulford Terminal - Sewage Treatment Plant Replacement - January 9 to May 24, 2023

*January 17 Update: Terminal construction will take place on the weekends of February 4-5 and 11-12 in addition to regular weekday hours. Contractors will comply with local bylaws and only start work after 8:00 am.

Please be advised that BC Ferries will be carrying out construction activities to replace the sewage treatment facilities at the Fulford Harbour Terminal. This work will begin on January 9 and will continue during weekdays until May 24, 2023.

  • The required work will include the use of equipment that may increase the normal sound levels within the terminal. The work will completed during weekday daylight hours, except for the weekend of February 4-5 and 11-12. The contractor will comply with local bylaws and not start work until after 8 am. All efforts will be made to minimize the noise for our neighbours.
  • During the construction period, the terminal washroom facilities will be closed. Portable washrooms will be available at the terminal for the use by our customers.
  • There will be a slight reduction to terminal vehicle holding capacity to facilitate the construction activities. Traffic control will be arranged to assist with managing overflow traffic on the roadway as required.
  • Drivers and customers are asked to follow the direction of staff, signage, and traffic control employees. We encouraged those travelling to arrive at the terminal earlier than usual for their intended sailing when travelling as a foot passenger.

For more information or traffic updates please follow @BC Ferries on Twitter, visit our website at bcferries.com, or call us toll free at 1-888-BCFERRY (223-3779).

UPDATE: Service notice - Temporary Vessel Replacement - Quinsam

During the scheduled refit of the Quinsam, an unexpected mechanical issue occurred with a critical engine component.

The Quinsam was expected to return to service on January 12, however, due to a supply chain issue related to equipment needed to complete the work, the refit will continue for approximately one more week.

The Quinitsa will continue to provide service on the Crofton – Vesuvius route.