December Project Update
Hello Quadra and Cortes Island community members,
I’m happy to share some exciting updates on the terminal rebuilt projects underway at Heriot Bay – Whaletown.
Construction
Significant work has advanced at Whaletown with much of the marine pile installation on schedule for completion by the end of this year. In January, the focus of the project will shift to preparing for the berth closure period, working offsite on prefabricated steel elements like the ramp and aprons. At Heriot Bay, we have been advancing electrical and hydraulic work, building the new waiting room, as well as installing concrete barriers and railings on the new trestle.
Work will pause between December 20th and January 5th for the holidays, so we can all take a break, recharge, and spend time with family and friends before returning in the new year.
Alternate service
A reminder that BC Ferries will provide alternate service between Cortes and Quadra during the Heriot Bay and Whaletown terminal closures from February 9th to March 1st, 2026. Learn more about this service and view updated barge / landing craft booking details in the previous project update directly below this one titled, October Engagement Summary and Project Update.
You’ll continue to hear from us through service notices, mail-outs, social media, sign boards, and this regular monthly update where you can learn more about these services and how we will continue to keep Cortes connected during berth closures.
If you have any questions, please don’t hesitate to contact our Customer Relations team at customer.relations@bcferries.com.
Thanks for reading and wishing you a happy holiday season!
Jeffrey Li
Project Manager
BC Ferries