Upcoming Geotechnical Work at Crofton Terminal
Between Sunday, July 26, and Thursday, July 30, 2026, contractors will be on-site completing underground electrical and utility work to support the Crofton Terminal Project.
Work will take place nightly between 8:00 p.m. and 5:00 a.m. Activities will include excavation, underground utility installation and restoration work. Temporary traffic control measures will be in place to safely accommodate construction activities, and there will be no impact to ferry service as a result of these activities.
Residents in the surrounding area may notice increased noise during these overnight work periods. Equipment used will generate additional noise, including, but not limited to, a hydrovac truck, excavator, saw cutter, compactor, paving equipment, and other construction tools and equipment. Every effort will be made to minimize impacts on local neighbours as we work efficiently and safely to complete this critical work. We apologize for this inconvenience.
The overnight utility work is necessary for the project, which includes building a new layby berth for anticipated new two-ship service, along with repairs and upgrades to the existing berth and trestle structures to improve safety and reliability.
The new two‑ship service anticipated to begin in 2027 will increase capacity by 20% and is expected to ease traffic congestion at the Crofton terminal by increasing sailing frequency, helping vehicle queues move more smoothly and reducing backups onto nearby roads.
To stay up to date with project information and construction updates, please subscribe for project page updates. This page is updated regularly with the latest project news, construction notices, and community information.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends