Provide Your Feedback on Upcoming Service Disruptions at Snug Cove

We Need Your Input

We’re upgrading the berth and marine structures at Snug Cove to keep ferries running safely and efficiently. Construction will require some sailing cancellations and berth closures and we’re asking for your help in planning for these service disruptions.

Project Overview

Work is slated to begin in November 2023 and continue until February 2024. Work will include steel reinforcement, replacement of mechanical items, and minor repair to the wingwalls and dolphins. In order to complete the work, sailing cancellations and berth closures will be necessary. We've held early meetings with key stakeholders, including Bowen Island Municipality to help us in planning to mitigate the impact of this work on the community. So far, this includes:

  1. Work is planned during the off-peak travel period (November - February).
  2. Work will be stopped over the holidays, to ensure holiday travel plans are not impacted.
  3. Most work will happen overnight (9:00pm - 5:00am) to minimize service disruptions.
  4. The regular schedule will be maintained one day each week.


We need your help now to complete the planning process. To learn more and provide your feedback, click here.

Share Provide Your Feedback on Upcoming Service Disruptions at Snug Cove on Facebook Share Provide Your Feedback on Upcoming Service Disruptions at Snug Cove on Twitter Share Provide Your Feedback on Upcoming Service Disruptions at Snug Cove on Linkedin Email Provide Your Feedback on Upcoming Service Disruptions at Snug Cove link